How we work

Six phases, one number you can build to.

Every Brott Development Group engagement follows the same disciplined sequence — from plan review to final reporting. The work below is an anonymized example of what a recent Pacific Northwest custom home looked like at the end of phase one.

The six phases

Phase one — pre-construction
01

Plan review

Comprehensive drawing audit

We comb every page of the architectural, structural, geotechnical, performance, and interior design drawings. Each scope item is marked, each assumption logged, and a structured list of questions is produced for the next meeting. Nothing enters the budget that hasn't first been seen and documented.

STEP 01 · PLAN REVIEW Blue-dot review 152 EA Blue-dot review · anonymized sample
02

Q&A meeting

Resolve open scope before pricing

Held early in the design process, this exercise eliminates assumptions. Architect-directed and client-directed finishes are recorded line by line. Decisions made here protect the architect's design intent before the budget gets near a value-engineering knife.

Step 02 · Q&A scope checklist
DivisionQuestionAnswer
Landscape planAvailable?In progress
3D SketchUp modelAvailable?Architect to send
Structural drawingsAvailable?Not yet, ETA tbc
Geotech reportAvailable?Not yet, ETA tbc
Civil drawingsAvailable?Confirmed
Site surveyComplete?Confirmed
Envelope engineerEngaged?Architect to send
Wildfire consultantRequired?Confirmed
Mechanical engineerEngaged?In progress
Electrical engineerEngaged?Confirmed
Acoustic consultantRequired?Not required
Lighting designerEngaged?Architect to send
Window packageSpecified?In progress
Cabinetry allowanceSet?Owner to confirm
Appliance packageSpecified?Owner to confirm
Stone & tile selectionsMade?In progress
Pool / spaIncluded?Confirmed
DemolitionRequired?Confirmed
Driveway finishSpecified?Not yet, ETA tbc
Site retainingEngineered?In progress
Q&A checklist · anonymized sample
03

Quantity survey & trade verification

Quantified takeoffs, ready for RFQ

All areas, quantities, and linear takeoffs are marked directly on the drawings and used to populate the budget. The same takeoffs are deliverable in digital format for direct use in request-for-quote packages with trades.

STEP 03 · QUANTITY SURVEY Crawl space 2,269 sqft Floor area 3,657 sqft Quantity survey · anonymized sample
04

Budget presentation & value engineering

Every line item explained

The detailed budget is walked through line by line with the architect, builder, and owner. Value-engineering candidates are identified and priced — not as cuts, but as informed decisions. Stakeholders approve, defer, or reject each one with the cost impact visible.

Step 04 · Budget & VE
Executive summary As-designed VE budget
Category subtotal $7,250,000$6,512,689
Contingency (10%) $725,000 $651,269
Contractor fee (10%) $797,500 $716,396
Subtotal$8,772,500$7,880,353
GST (5%) $438,625 $394,018
Grand total$9,211,125$8,274,371
Value engineered
−$936,754
Selected VE initiatives
Existing garage re-and-re — phase to a later date−$218,027
Painting — delete exposed rafter & soffit detail (main + coach house)−$185,377
Mechanical — delete sauna and Nu Heat floor zones−$125,350
Countertops — mid-level Caesar Stone, coach house−$112,250
Skylights — delete two passage skylights in basement bedrooms−$96,500
Electrical — delete Flexa & linear lighting packages−$89,500
Interior doors — MDF in lieu of European Morfine, coach house−$84,750
Equipment — Fischer Paykel in lieu of Miele / Sub-Zero / Wolf, coach house−$25,000
Budget executive summary · anonymized sample
Phase two — through construction
05

Tendering

Compete trades against the IFP set

From the moment the issue-for-pricing drawings are released, we run the tendering process across all trade scopes. The objective: lock seventy-five percent of the budget at fixed price before construction starts.

Step 05 · Tendering — Tile labour · bid leveling
Scope Budget Trade A Trade B Trade C Trade D
Foyer & entry$4,200$3,840$4,210$5,375$4,090
Powder room$2,100$1,920$2,180$2,640$2,015
Mudroom & laundry$5,500$5,260$5,840$7,120$5,395
Primary ensuite$13,000$12,475$13,290$17,840$12,995
Family bath$8,000$7,640$8,275$10,490$7,855
Outdoor terrace$14,200$13,715$14,980$20,320$14,250
Total$47,000$44,850$48,775$63,785$46,600
Summary vs budget
Trade A−$2,150
Trade B+$1,775
Trade C+$16,785
Trade D−$400
Bid-leveling sheet · anonymized sample
06

Reporting

One page. The full picture.

Throughout construction, a single-page summary on cost and schedule is delivered on a defined cadence, backed by the supporting detail. Owners stay in the driver's seat. Builders stay focused on the build. Architects stay focused on design.

Step 06 · Reporting
Executive summaryValue
Approved construction budget$3,975,420
Total change request value$812,640
Forecasted contingency usage beyond fund$0
Forecasted contingency as % of budget0%
Current budget expectation$4,788,060
Forecasted budget expectation$4,712,335
Costs to date$3,234,890
Costs to come$1,477,445
Percentage complete68%
Percentage remaining32%
Total contingency$186,520
Contingency used to date$84,170
Contingency used (% of contingency)45.1%
Forecasted contingency usage$96,840
Forecasted contingency usage (% of contingency)51.9%
Forecasted contingency remaining$89,680
Budget composition
$3.98M Approved
CHG ORD
Approved $3.98M Change orders $813K
Current expectation $4.79M
Completion
68% complete
050%100%
Forecast at completion $4.71M / $4.79M
Contingency usage
45.1%
+
050%100%
Used to date45.1%
Forecast51.9%
Remaining$100,000
Executive summary report · anonymized sample
Discuss your project

If you'd like this kind of detailed consideration on your next custom home, start with a fifteen-minute call.

We are happy to discuss your project further.